济南电缆桥架作为布线工程的一个配套项目,现在尚无专门的标准辅导,一个生产厂家的标准程式缺少通用性,因而,设计选型进程应依据弱电各个系统缆显得类型、数量,合理选定适用的桥架。
Jinan cable bridge as a supporting project of wiring engineering, there is no special standard guidance, a manufacturer's standard program is lack of universality, therefore, the design and selection process should be based on the type and quantity of each weak current system cable, reasonable selection of suitable bridge.
断定方向: 依据修建平面布置图,结合空调管线和电气管线等设置状况、便利修理,以及电缆路由的疏密来断定电缆桥架的路由。在室内,尽可能沿修建物的墙、柱、梁及楼板架起,多么使用归纳管廊架起时,则应在管道一侧或上方平行架起,并考虑引下线和分支线尽量防止穿插,如无其它管架借用,则需自建立(支)柱。
Determine the direction: determine the route of cable bridge according to the construction layout plan, the setting condition of air conditioning pipeline and electrical pipeline, the convenience of repair, and the density of cable route. Indoors, it should be erected along the wall, column, beam and floor of the building as far as possible. When the pipe gallery is used, it should be erected parallel on one side or above the pipe, and the down lead and branch line should be considered to avoid interpenetration as far as possible. If there is no other pipe rack to borrow, it is necessary to establish (support) column by itself.
荷载核算:核算电缆桥架主干线纵断面上单位长度的电缆分量。断定桥架的宽度:依据布放电缆条数、电缆直径及电缆的距离来断定电缆桥架的类型、标准, 托臂的长度,支柱的长度、距离,桥架的宽度和层数。
Load Accounting: calculate the cable component per unit length on the vertical section of the main line of cable bridge. Determine the width of the cable tray: determine the type and standard of the cable tray, the length of the bracket, the length and distance of the pillar, the width and number of layers of the cable tray according to the number of cables, the diameter of the cable and the distance of the cable.
安装方法:依据场所的设置条件断定桥架的固定方法,挑选悬吊式、直立式、侧壁式或是混合式,连接件和紧固件一般是配套供给的,此外,依据桥架结构选折相应的盖板绘出电缆桥架平、剖面图,部分部位还应绘出空间图,开列材料表。如与电力电缆桥架合用时,应将电力电缆和弱电电缆各直一侧,中心选用隔板分隔。
Installation method: determine the fixing method of the cable tray according to the setting conditions of the site, and select the suspension type, vertical type, side wall type or mixed type. The connectors and fasteners are generally supplied together. In addition, according to the bridge structure, select and fold the corresponding cover plate, draw the plane and section drawings of the cable tray, and draw the space diagram for some parts, and list the material list. If it is used together with power cable bridge, the power cable and weak current cable should be separated on each straight side, and the center should be separated by partition.